Big week at The Block with a hive of activity pumping.
This week has seen:

- Bricks Completed - sweet
- Moulding installed in Oak Park Facade
- Balcony rendered (but not with final colour coat of Dune)
- Plumbers in to lay storm water around the house and pressurised pits install
- internal doors. jams and skirting boards and architraves nearing completion
- Garage Roof trusses installed
- Cabinetry installation finalised - waiting for stone counter / bench tops
- TV antenna installed
- eaves painted
- top half of bricks cleaned and joint filled

Seems that there is a crescendo effort being thrown in before christmas approaches which is fantastic.